News & Events
Media Contacts
Chris Bratthauar
Manitowoc Cranes
717.593.5348
Chris.Bratthauar@manitowoc.com
Leslie Shalabi
SE10 Creative
608.251.6280
shalabi@se10.com
RSS Feed
RSS Feed
Subscribe to the latest Manitowoc news
News Release

Manitowoc crawler cranes keep runway addition on schedule

2/2/2012 Boston, Massachusetts, United States

Four Manitowoc crawler cranes are working on an expansion project at Logan International Airport in Boston, Mass. The cranes, three Manitowoc 999s and a barge-mounted Manitowoc 2250, are helping the contractor meet the project's demanding schedule.

The project consists of lengthening the airport's longest west-to-east runway by building a 600 ft x 300 ft pier out into Boston Harbor. The Manitowoc 999s are being used in all aspects of the operation from driving 18 in (45 cm) square precast piles and setting the precast concrete pile caps, to placing specially designed precast concrete beams, called NEXT (Northeast Extreme Tee) beams.

The Manitowoc 2250 is doing the bulk of the marine work from a 54 ft x 180 ft barge. J. F. White Contracting Co., the project's general contractor, is renting the cranes from Baldwin Crane and Sterling Equipment.

Jim Beach, project manager at J.F. White, said the greatest challenge has been the tight timeline and the constraints of working on a major runway within a busy, operating international airport.

"The schedule has been really challenging, especially since October, at which point we had to return the runway back to airport control for use at night," said Beach. "We knew the 999s would be a good fit on this project because they have the capacity and reach coupled with the speed and mobility to efficiently move on and off the pier."

To meet the demands of the schedule and to ensure the airport has unrestricted access to the runway at night, the cranes move off the pier to a staging area every evening. The staging area is more than 700 ft from the jobsite, and moving the cranes takes approximately 80 minutes at the start and end of each day.

To move the cranes rapidly on and off the narrow pier, J.F. White constructed a 35 ft x 35 ft rotating platform between the pier and the land to enable the cranes to handle the vertical disparity between the two working elevations. Each morning, after maneuvering on to the platform, the platform rotates 90 degrees so the cranes pull off the platform onto the pier. The same process takes place in reverse every evening. This has saved the time and space that would be otherwise required to move three 999s on and off the deck.

A streamlined process has ensured the cranes are on the jobsite as quickly as possible, and has allowed the project, which began in July 2011, to break for winter on November 20.

The 275 USt capacity Manitowoc 999s are configured with 190 ft of main boom, and the 330 USt capacity Manitowoc 2250 is configured with 160 ft of main boom. The heaviest elements in the construction of the pier are the concrete NEXT beams, which are 10 ft wide x 40 ft long and weigh approximately 50 USt each.

The extension of the runway, once complete, will enable Logan Airport to land larger jets such as 747s and 777s on the runway when other airports are forced to close due to inclement weather. The expansion is part of an FAA mandated safety improvement project and is expected to be complete by November 2012.
About The Manitowoc Company, Inc.
The Manitowoc Company, Inc. (“Manitowoc”) was founded in 1902 and has over a 117-year tradition of providing high-quality products and support services that are tailored to customers’ needs. Its 2019 net sales were approximately $1.83 billion. Manitowoc is one of the world's leading providers of engineered lifting solutions. Through its wholly-owned subsidiaries, Manitowoc designs, manufactures, markets and supports comprehensive product lines of mobile telescopic cranes, tower cranes, lattice-boom crawler cranes, boom trucks and industrial cranes under the Grove, Potain, Manitowoc, National Crane, Shuttlelift and Manitowoc Crane Care brand names.
 Processing Request